Kitchens look like a cabinet-and-benchtop job, but most of the cost and nearly all of the risk is in what sits behind the cabinets: wiring, plumbing, ventilation, linings and, in an older house, materials that need testing. Order matters more than anything else. Get it wrong and trades undo each other's work, or something that should have been inspected is buried under tiles.
Check consent. Many kitchen alterations need no building consent, but it depends on what changes. Schedule 1 of the Building Act 2004 exempts alterations to existing sanitary plumbing if the total number of sanitary fixtures is not increased and no specified system is affected (water heater alterations excepted), work on internal linings and finishes in an existing dwelling, and penetrations up to 300 millimetres across. Removing a wall, moving a sink to a new position that needs new drainage, or adding a fixture is different. Internal wall work is exempt only if the wall is not load-bearing, bracing, a firewall, part of a specified system, or masonry. Exempt work is still conditional under section 42A. Read the wording in the Building Act 2004 or ask the council.
Test for hazardous materials. BRANZ's Level guide says asbestos-based products were widely used from the 1920s to the mid-1980s, including vinyl floor coverings, wall claddings, adhesives and paints. It also reports a February 2023 case in which a Christchurch flooring company was fined $52,500 for failing to identify that old vinyl being replaced contained asbestos. Kitchens are full of old vinyl, so test before the floor comes up. Health NZ advises presuming that paint in buildings from the 1980s or earlier is lead-based. See the Level asbestos page and Health NZ lead guidance.
Design the layout and services together. Decide appliance types and positions before any rough-in, because they set the electrical circuits, the plumbing and the extraction.
Disconnect and cap services, using authorised tradespeople for electrical and gas, and then remove cabinets, benchtops, old linings and flooring as planned. Bag and dispose of contaminated material properly. Look at what the removal reveals: rot behind the sink, old leaks, borer, and wiring that has been altered over the years.
Repair framing, replace damaged floor or wall substrates, and complete any structural alterations, such as a wall removal, with the required inspections. Doing this before services keeps the rough-in work clean.
This is the stage where the kitchen's function is fixed.
Insulate and line walls and ceilings once the wiring and plumbing are checked. Level says surfaces exposed to water splash must be impervious and easy to clean. For paint finishes, plasterboard should be stopped to level 4 or 5, and standard-grade board suits areas that are normally dry or occasionally splashed; areas around sinks warrant care, and tiled splashbacks go onto a firm, stable substrate. Cabinetry made from MDF and particleboard is vulnerable to water, which Level lists among the causes of wet-area damage, so seal edges and cut-outs at the sink.
Lay flooring before the cabinets if the design calls for it, or after if you want to be able to replace the floor without moving them. Paint ceilings and walls before the cabinets go in, leaving only touch-ups for after installation. Kitchen walls and ceilings are best done with coatings that clean easily; BRANZ notes that high-gloss coatings are easier to clean and less affected by mould, while semi-gloss suits low wear and wetting.
Install base cabinets, benchtops, then wall cabinets, scribing as you go to uneven old walls and floors. Fit the splashback after the benchtop, and seal movement joints with flexible mould-resistant sealant. Template benchtops only after cabinets are fixed and level.
Fit taps, appliances, power outlets and the extractor. Have electrical work tested and certified, and plumbing checked for leaks under working pressure. Record the work, and gather certificates, warranties and any council sign-off.
Rules and guidance change, so confirm current requirements with your council before work starts.