Finishing new plasterboard after a renovation

New plasterboard is one of the least dramatic parts of a renovation and one of the easiest to get wrong. Walls that looked fine under bare board show every joint once a glossy coat goes on, and a bathroom lining that was never sealed can swell long before the first leak is noticed. Finishing is a sequence of small decisions, and most of them depend on what the room will be used for.

What you may be dealing with before the board goes up

In an older house, new plasterboard rarely goes onto a clean slate. It is fixed over old framing, next to old linings, and sometimes after demolition of materials that need care. Asbestos-based products were widely used from the 1920s to the mid-1980s, and BRANZ's Level guide lists decorative ceilings, wall claddings and sheet linings among the places they turned up. Old paint may also be lead-based; Health NZ advises presuming that anything built in the 1980s or earlier carries it. Both should be dealt with before new board is fixed, because patching and blending the new lining into the old walls is exactly the work that creates dust.

Information on handling those materials is on the Level asbestos page and the Health NZ lead page.

Consent and the rules around lining work

Replacing or adding internal linings in an existing dwelling is listed in Schedule 1 of the Building Act 2004 as work that does not need a building consent. The exemption is conditional. Work must still comply with the Building Code to the extent the Act requires, the building must not end up less compliant than before, and the work must not breach any other enactment. The conditions are set out in section 42A and Schedule 1 of the Act.

Linings are not always only linings. In some houses the board is part of the bracing or a fire-rated wall, and altering it is a different category of work. If a wall has any structural or fire role, ask the council before you strip it.

Stopping levels: how smooth is smooth enough

Plasterboard finishes are described in levels. BRANZ's guidance says board for a paint finish should be stopped to level 4 or 5, while level 3 is enough for a flexible sheet or tiled finish. The difference matters because gloss paint and raking light exaggerate imperfections. A wall that looked flat under matt paint can look like a map of its joints under a semi-gloss coating.

Plan the stopping level around the coating and the light:

Sealing and primer

Plasterboard soaks up coatings unevenly. The paper face, the stopping compound and any patched older surface each absorb differently, so the finish dries with visible differences unless the whole surface is sealed. In wet areas, BRANZ says standard-grade board suits areas that are dry or only occasionally splashed, with an oil-based sealer coat and at least three coats of water- or oil-based semi-gloss or full-gloss paint. Water-resistant grades are available and must be protected from direct wetting. Behind tiles in a shower or around a bath or basin, water-resistant board needs a waterproofing system, and BRANZ recommends a membrane behind tiles in all splash areas.

For wallpaper, the board needs to be at least level 3 and sealed with a water-resistant sealer before vinyl-coated paper goes on.

The full guidance is on the Level wet area wall and ceiling linings page.

Choosing a coating that suits the room

BRANZ's guidance covers sheen as well as chemistry:

For a bathroom, the practical result is a higher sheen than most people choose for a living room, and a surface sealed as well as painted. That is a good reason to talk about the coating with whoever does the stopping, not after it.

The order of jobs

A sensible order for a room with new board:

  1. Fix and tape the plasterboard once wiring, plumbing and insulation are signed off behind it.
  2. Stop the joints and screw heads, building up in thin coats and letting each dry.
  3. Sand lightly, with dust control, and clean the surface.
  4. Seal or prime the entire surface.
  5. Inspect in raking light and correct flaws before the finish coats.
  6. Apply the finish coats, with any wet-area membrane and tiling done before painting adjoining surfaces.

Do not rush step five. A flaw that is obvious in the primer is a ten-minute fix. After the third coat of gloss it is a re-do.

When specialist finishing is worth paying for

Large rooms with long, lit walls, high-gloss specifications, and renovations where new board meets old plaster all benefit from an experienced finisher. A painter who specialises in painting new plasterboard will talk about stopping levels, sealers and lighting conditions at the quoting stage, which is the time to settle them. Painters such as Eggshell & Co set out the stages of a renovation finish on their own pages, and it is worth comparing that sequence with whatever a quote offers.

Guidance and regulations change, so check the current versions of the sources below.